Highway 58 And Viking Road Construction

Construction project's activity and road closures can be found on this page.

Road Closures:

This is to notify the public of a road closure of the Forks Road Bridge. This closure is require for public safety. The bridge will be closed November 2, 2018 and remain closed until further notice. The bridge will remain open to pedestrian traffic only at all times. EMERGENGY SERVICES WILL NOT HAVE ACCESS. The detour will utilize Highway 58, Highway 58A and Canal Bank Street. For more details, read the media release.

For any questions regarding the above please contact Mark Slade at 905 735 1700 ex 2212. Traffic and Parking Operations

Road detour Forks Road


Construction Activity for Municipal Subdivisions and Niagara Region Projects:

80% Complete
Location/Description: To install inside servicing in subdivision and servicing on Memorial Park Drive.
Activity: Primary servicing complete. Deficiencies under review. Building ongoing.

80% Complete
Location/Description: Servicing for new subdivision off Clare Avenue near Fitch Street Phases 1-4
Activity: All servicing complete. Top asphalt complete for phase 2. Building ongoing for phases 3 and 4.

90% Complete
Location/Description: Servicing for new subdivision off North Valley Drive near the intersection of Vanjo Dr and Clare Ave
Activity: Review of deficiencies scheduled in July 2021.

80% Complete
Location/Description: Servicing for new subdivision bounded by Webber Road, South Pelham Road and Gaiser Road
Activity: Phases 3 building ongoing. Review of deficiencies expected to be scheduled in 2021 for phase 4-6.

60% Complete
Location/Description: North West corner of Webber Road and South Pelham Road
Activity: Primary servicing complete. Building ongoing.

95% Complete
Location/Description: 40 McCabe St former recreational centre. Bounded by McCabe and Bradley
Activity: Building and top asphalt complete. Subdivision under maintenance period.

40% Complete
Location/Description: North East Corner of South Pelham Road and Webber Road. New Seniors care facility and row of townhouses on site.
Activity: Primary servicing and base asphalt complete. Deficiencies under review.

80% Complete
Location/Description: Servicing for new development off of McCabe
Activity: Primary servicing complete. Building ongoing.

90% Complete
Location/Description: New Subdivison south of Forks Road at the East end of Forks.
Activity: Primary servicing complete. Building ongoing.

20% Complete
Location/Description: Design Build Contract for a new Fire hall Headquarters on the old Atlas lands off East Main St. Project incorporates land cleanup, design and build of new fire hall and training center.
Activity: Initial site works completed. Working through Shop Drawing package.
Traffic /Service Disruption: One Lane to be maintained at all time

99% Complete

Location/Description: Full road Reconstruction of Edgar St. from Church St. to Northcote Ave., Weller Ave. from Edgar St. to West limit, Elmview St. from Edgar St. to Niagara St., Northcote Ave from Edgar St. to Niagara St. & Charlotte Court from Northcote Ave to South limit.
Activity: In Warranty
Traffic /Service Disruption: No impacts

0% Complete

Location/Description: North of Webber Road, West of Clare Avenue, East of South Pelham Road, North of Westcreek Cres. It was supposed to be Westcreek Ph 2 but they switched it up.
Activity: Approval

0% Complete

Location/Description: This location is east of the railway and north of Forks Road
Activity: Approval. Earthwork has commenced.

5% Complete

Location/Description: Dain West is the former John Deere property being developed by Empire Homes
Activity: Portion of work under building permit. Subdivision design forthcoming.

0% Complete

Location/Description: The lands of the former Ucar Carbon products. East of Canal Bank St, North of Hwy 58A
Activity: Site clean up and remediation

95% Complete

Location/Description: South Pelham Road westerly Including part of Gaiser Road and Julia Drive
Activity: Building and top asphalt complete. Phase 1-2 under maintenance period.

95% Complete

Location/Description: North of Gaiser Road East of South Pelham Road, West of Clare Avenue
Activity: Phase 1-2 currently completing final inspections before assumption. Phase 3-5 Top asphalt complete. under maintenance period.

95% Complete

Location/Description: North west and south east corners of Gaiser Road and South Pelham Road.
Activity: Building complete. All infrastructure installed under Sparrow Meadows

20% Complete

Location/Description: North of Webber Road, East of Murdoch road in the City of Welland
Activity: construction commenced. installation of servicing ongoing.

50% Complete

Location/Description: Lands North of Sauer including Iva, Louise and Bradley extensions
Activity:primary servicing complete. Base asphalt and curbs installed.

100% Complete

Location/Description: Missing Link Sidewalk Replacement at the following locations:
- Maple Park Dr (Clare to Lloyd)
- Clare Ave (Maple Park to Thorold)
- Abby Rd (Carlton to Gram)
- Carlton Rd (Thomson to Forest)
- Forest Rd (Carlton to Gram)
- Gram Ave (Thomson to Woodlawn)
- Edgewood (Abbey to Forest)
- Thomson Rd (Carlton to Gram)
Activity: Project completed
Traffic /Service Disruption: One lane of traffic to be open at all times

100% Complete

Location/Description: Road Resurfacing - Top Lift Asphalt at the following locations:
- Aqueduct Street from Niagara St to Thorold Rd
- Church Street from Niagara St to West Limit
- Fell Street from Fitch St to Church St
- Fitch Street from First Ave to Chotwell St
- Highland Gardens from West Limit to East Limit
- Merritt Street from Somerville Ave to Niagara St
- Pine Street from Niagara St to Aqueduct St
- Shotwell Street to Fitch St to Church St
- Somerville Avenue to Fitch St to Merritt St
- Elgin Street to Shortwell St to Niagara St
- Green Pointe Dr from 39 Green Pointe Dr to 193 Green Pointe Dr
- Abbott Rd from Northgate Dr to Green Pointe Dr.
- Harold Avenue from East Main Street to Major Street
- Wellington Street from East Main Street to Major Street
- Hagar Street from Crowland Avenue to Wellington Street
- Harrison Avenue from Southworth Street to Empress Avenue
- Tanguag Avenue from Wellington Street to East Limit
- Prom Richelieu from Tanguag Avenue to Wellington Street
- Ross Street from Bruce Street to Downs Drive
Activity: Project completed
Traffic /Service Disruption: One lane of traffic to be open at all times

85% Complete
maps Logo Drawings for the Road Rehabilitation – Part 1

Location/Description:
Cola Street (Centennial Drive to Lindel Crescent)

  • Asphalt Surface Replacement
  • Curb and Sidewalk (North side only) Replacement

Nottingham Court (Rolling Acres Drive to South Limit

  • Asphalt Surface Replacement
  • Curb and Sidewalk Replacement

Dougherty Crescent (Rice Road to East Limit)

  • Asphalt Surface Replacement
  • Curb and Sidewalk Replacement

Northgate Drive (First Avenue to #112 Northgate Drive

  • Asphalt Surface Replacement
  • Curb and Sidewalk Replacement

Abbey Road (Niagara Street to Gram Avenue)

  • Asphalt Surface Replacement
  • New Curb and Sidewalk (North side only) Installation

Activity: awaiting landscaping restoration
Traffic /Service Disruption: One lane of traffic to be available at all times, short duration road closures may be required.

90% Complete

Location/Description: Watermain replacement program for the following streets:
State St - Watermain, water services, sanitary laterals, full road, curb & sidewalk replacement
Albert St - Watermain & water service replacement
Cady St - Watermain, water services, sanitary laterals, full road & curb replacement
Sumbler Rd - Watermain, water services & road
Activity: Sumbler Road complete. State St. complete awaiting landscaping restoration. Albert St. complete. Cady Street underground complete, awaiting paving and landscaping
Traffic /Service Disruption: One lane of traffic to be open at all times - Minor full road closure may be required

85% Complete

Location/Description: Servicing for new subdivision along West side of Denistoun, North of West Main Street.
Activity: Servicing complete. Deficiencies under review.
Traffic /Service Disruption:

45% Complete

Location/Description: Servicing for new subdivision along East side of Colbeck Drive, South of Webber.
Activity: Servicing complete.
Traffic /Service Disruption:

0% Complete

Location/Description: New development Extending Regatta Drive to the South and connecting to Kingsway.
Activity: Approval
Traffic /Service Disruption:

0% Complete

Location/Description: New development Extending Wellandvale Drive to the East.
Activity: Under subsdivision design review.
Traffic /Service Disruption:

70% Complete

Location/Description: Commercial development at North end of River Road and Power Drive.
Activity: Primary servicing complete. Deficiencies under review.
Traffic /Service Disruption:

90% Complete

Location/Description: Servicing for new development lots at the corner of Hilda Street and Aqueduct Street.
Activity: Servicing complete. Building ongoing.
Traffic /Service Disruption:

60% Complete

Location/Description: New subdivision development South of Daimler Parkway.
Activity: Primary servicing complete. Building ongoing.
Traffic /Service Disruption:

0% Complete

Location/Description: Privately owned development North of Daimler Parkway.
Activity: Phase 4-5 under design review.
Traffic /Service Disruption:

70% Complete
pdf Logo Notice to Residents Letter
maps Logo Walts
maps Logo Barrington And Fairlawn
maps Logo Glen Park Court

Location/Description: Road Rehabilitation Program for the following Streets:
Barrington Drive - Endicott Terrace to Aquador Drive
Fairlawn Crescent - Endicott Terrace to Barrington Drive
Walts Street - Clare Avenue to Walts Drive
Glenpark Court - Glenpark Drive to North Limit
Lisa Court - Loyalist Drive to South Limit
Activity: Paving on Walts St to be completed the week of December 13. Awaiting landscaping restoration
Traffic /Service Disruption: One lane of traffic to be open at all times possible. Minor periods of full road closure may be required.

90% Complete
pdf Logo Notice to Residents
maps Logo Westmount
maps Logo Riverview

Location/Description: Cast iron watermain replacement program for Westmount Cres. & Riverview Dr.
Activity: All watermain related works are finished. Final driveway restoration wrapping up. Final surface works to be completed in Spring 2022.
Traffic /Service Disruption: N/A. Spring construction will require lane closures for surface works

95% Complete

Location/Description: Storm Water Management Pond rehabilitation project located at 541 South Pelham Road
Activity: Complete, final seeding restoration spring 2022
Traffic /Service Disruption: Minimal disruption to traffic, one lane to be left open at all times

50% Complete

Location/Description: Humberstone Road and Southworth Street - between Townline Tunnel Road and Gordon Street
Activity: Regional sewer works in progress. Local watermain and sanitary works have been completed. Base course of asphalt on Southworth expected to be complete in the middle of December
Traffic /Service Disruption: One lane of traffic to be maintained at all times. Localized day closures required for the Regional works

15% Complete

Location/Description: Culvert replacement at River Road, Colbeck Dr & Ridge Rd.
Activity: Culvert on River Road currently being worked on.
Traffic /Service Disruption: Contractor to maintain one lane of traffic when possible.

40% Complete
pdf Logo Notice to Residents

Location/Description: Full road reconstruction and replacement of underground infrastructure on Forks Road from Crescent Drive to the east limit.
Activity: Construction on Forks Road is ongoing.
Traffic /Service Disruption: One lane of traffic is to be open at all times where possible. There may be minor periods (less than 5 minutes) of full road closure required.

Source: https://www.welland.ca/Traffic/construction.asp